Mumbai's ambitious biomining project at Mulund dumping ground faces another setback. The contractor, citing fuel supply disruptions from the West Asia war, has requested a third extension. This geopolitical event is deemed a 'force majeure' by the firm, impacting machinery operations and transport. Civic officials are reviewing the request, which follows previous delays due to Covid-19 and Cyclone Tauktae.
Mumbai's ambitious biomining project at Mulund dumping ground faces another setback. The contractor, citing fuel supply disruptions from the West Asia war, has requested a third extension. This geopolitical event is deemed a 'force majeure' by the firm, impacting machinery operations and transport. Civic officials are reviewing the request, which follows previous delays due to Covid-19 and Cyclone Tauktae.